Bag air duct debugging

Bag air duct debugging After installation, the fiber fabric air duct should be adjusted. 1. Before debugging the air duct system, need to clean the system pipe. Before connecting to the system, it is necessary to clean the iron duct (which can open the fan to blow out some construction waste) to ensure good sanitary performance of the system and prevent building dust from blocking the system. 2. During installation and debugging, the pressure of the air cabinet is divided into 2 -3 grades (such as 100PA, 200Pa) when it starts to rise to the working pressure gradually, avoiding the damage of the end of the air duct system caused by the instantaneous high pressure. 3. Open the fan to inflate the duct system pipe. The air duct system pipes along the whole suspension system tidied up to form a straight state, if there is a droop in the middle, need to add hanging point again, to ensure the horizontal state of the air duct.